6 Steam Turbine and Generator Set
6.1 General Requirements
6.1.1 The travelling crane inside the steam turbine generator workshop has been trial run,and inspected to be qualified by the special equipment supervision and inspection organization.
6.1.2 During construction,the temperature inside the workshop should not be below 5℃.