GB51005-2014水泥工厂余热发电工程施工与质量验收规范(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

5.3 Installation of Dust Separator

5.3.1 The field assembly of dust separator shall comply with the equipment technical documentation.

5.3.2 The on-site opening of separator shall be completed before the wear-resisting lining is constructed.

5.3.3 The surface of wear-resisting lining shall be smooth.