6.2 Billet Shears
General item
6.2.1 The press assembly,hot assembly and cold assembly of the mechanical parts and connection bolts shall meet the requirements of design documents.
Inspection quantity:30% sampling inspection and not less than 4 positions.
Inspection method:observation,check installation quality record.
6.2.2 The allowable installation deviation of base plate for billet shears shall be in accordance with those specified in table 6.2.2.
Inspection quantity:total number inspection.
Inspection method:it should be in accordance with those specified in table 6.2.2.
Table 6.2.2 Allowable installation deviation of base plate for billet shears
6.2.3 The allowable installation deviation of billet shear frame shall be in accordance with those specified in table 6.2.3.
Inspection quantity:total number inspection.
Inspection method:it should be in accordance with those specified in table 6.2.3.
Table 6.2.3 Allowable installation deviation of billet shear frame
6.2.4 The allowable installation deviation of blade changing device for billet shears shall be in accordance with those specified in table 6.2.4.
Inspection quantity:total number inspection.
Inspection method:it should be in accordance with those specified in table 6.2.4.
Table 6.2.4 Allowable installation deviation of blade changing device for billet shears