9.9 Inspection and Documentation
9.9.1 The quality acceptance for the erection of equipment and pipes in fuel oil system shall be carried out in stage by the construction company,the supervision company and the Owner.
9.9.2 The following certification and records shall be ready for the construction quality acceptance:
1 Certification for the corrosion protection of buried pipes in fuel oil system.
2 Certification for hydrostatic test of the equipment and pipes in fuel oil system.
3 Certification for the blowing and flushing of pipes in fuel oil system.
4 Certification for the oil circulating test of fuel oil system.
5 Records of the fabrication,erection and filling water test for metallic oil tanks.
6 Maintenance and erection records of the oil pump.
7 Erection records of the equipment and pipes in fuel oil system.