2.6 Documents for Completion Acceptance of Works

2.6.1 During the completion acceptance,the signed certification shall be exchanged and the following technical documents shall be provided:

1 As-built drawings.

2 Documents related design modification and material substitution.

3 Certificates of quality for main equipment,apparatus and materials,materials list,and receiving acceptance inspection record.

4 Record of concealed works.

5 Technical documents provided with equipment.

6 Records of construction and installation.

7 Commissioning test record of electrical equipment.